Mainnet Deployment Runbook

Purpose and Scope

docs/deployment-guide.md and docs/deployment-checklist.md already document what the deployment process involves in prose and checklist form. This runbook is the missing operator-facing, linear script: the exact sequence an operator follows during an actual mainnet deployment window, start to finish, with explicit go/no-go gates. Follow this document top to bottom during a real deployment; use the other two as reference material when a step needs more explanation.

Two operators minimum are required for any mainnet deployment: one executes commands, one reads them back before submission. Neither operator holds both the deployer key and the admin key.


0. Pre-Deployment Checklist (Go/No-Go Gate)

Do not proceed past this section unless every item is checked.

  • All tests pass on the exact commit being deployed: cargo test (clean, not from memory of a prior run)
  • cargo audit and cargo deny check both report zero unresolved advisories (see deny.toml)
  • The commit has been through code review and, for contract changes, the review referenced in docs/security-audit-checklist.md is complete
  • WASM artifacts are reproducibly built (see docs/deployment-checklist.md "Artifact Verification") and the build hash is recorded in the deployment ticket
  • Deployer account and admin account are two distinct funded mainnet Stellar accounts (never the same key — see §1)
  • Admin account is a multisig (see docs/deployment-guide.md §4.2) with signers reachable and available during the deployment window
  • A rollback owner is named and has read §4 of this runbook before deployment starts
  • Monitoring dashboards (see docs/monitoring-guide.md) are open and confirmed reachable before the first transaction is submitted
  • A maintenance/deployment window has been communicated to any dependent services (API server, dashboard)
  • .env mainnet values are staged but contract ID fields are still blank (they get filled during §2)

If any box is unchecked, stop. Do not deploy under time pressure with an incomplete checklist — a rushed mainnet deployment is the single most common cause of the incidents in docs/disaster-recovery.md.


1. Funding

Mainnet has no friendbot. Funding must come from a real XLM source.

  1. Acquire XLM for both the deployer and admin accounts through a licensed exchange or anchor (e.g. an on/off-ramp your organization already has compliance clearance for). Do not use a testnet faucet workflow — it does not exist on mainnet and any tool claiming otherwise is not talking to the real network.
  2. Fund the deployer account with enough XLM to cover: 3 contract installs/deploys (~1–2 XLM each), plus a buffer for retries — budget 10 XLM minimum.
  3. Fund the admin account(s) — every signer in the admin multisig needs its own account funded with enough XLM to cover the base reserve (currently 1 XLM per account plus 0.5 XLM per additional signer/entry) and transaction fees for initialization and future admin operations. Under-funding the admin multisig is a common cause of stuck initialization — verify each signer independently:
    stellar account show <signer-alias> --network mainnet
  4. Record every funding transaction hash in the deployment ticket before proceeding — this is your audit trail if a rollback or dispute happens later.
  5. Confirm balances one more time immediately before the deployment window opens (balances can silently drop if a key was reused elsewhere):
    stellar account show deployer --network mainnet

2. Deployment Steps

2.1 Contract upload (install + deploy)

Follow docs/deployment-guide.md §2–3 to build and deploy quorum_proof, sbt_registry, and zk_verifier in that order. Order matters operationally (not technically — the contracts don't yet reference each other's addresses at install time) because quorum_proof is the contract every subsequent smoke test depends on, so deploying it first lets you catch build/deploy issues before spending fees on the other two.

After each stellar contract deploy, immediately:

  1. Paste the returned contract ID into the deployment ticket
  2. Update the corresponding .env field
  3. Confirm the contract exists on-chain before moving to the next one:
    stellar contract info --id $CONTRACT_QUORUM_PROOF --network mainnet

Do not deploy all three back-to-back without this per-contract confirmation — if quorum_proof deployment silently failed (e.g. RPC timeout returning a stale ID), you do not want to discover it after already spending fees on the other two.

2.2 Initialization

Follow docs/deployment-guide.md §4 to call initialize(admin) on each contract. Two operational rules beyond what that section covers:

  1. Initialize in the same order you deployed (quorum_proof → sbt_registry → zk_verifier). quorum_proof::initialize also registers the v1 metadata schema as the active schema as a side effect — verify this schema registration succeeded (§3.2) before initializing the other two contracts, since a failure here is cheaper to fix before other contracts are live.
  2. Use the admin multisig address, not an individual signer's address, as the admin parameter. Passing an individual signer's address by mistake means that signer alone controls the contract going forward — this cannot be undone without a full redeployment (§4.3).

2.3 Cross-contract configuration

If this deployment wires sbt_registry or zk_verifier to trust quorum_proof (e.g. authorizing quorum_proof as the only caller allowed to mint SBTs, or registering the verifying key zk_verifier will check credential proofs against), perform that wiring now, immediately after all three contracts are initialized and before any real traffic is routed to them. Record every configuration call's transaction hash in the deployment ticket — these are exactly the calls a rollback needs to identify and potentially reverse.


3. Post-Deployment Verification

Do not announce the deployment as complete until all of these pass.

3.1 Basic liveness

stellar contract invoke --id $CONTRACT_QUORUM_PROOF --network mainnet -- get_admin
stellar contract invoke --id $CONTRACT_SBT_REGISTRY --network mainnet -- get_admin
stellar contract invoke --id $CONTRACT_ZK_VERIFIER --network mainnet -- get_admin

Confirm each returns the admin multisig address recorded in the deployment ticket — not an individual signer's address (see §2.2).

3.2 Schema/state sanity

stellar contract invoke --id $CONTRACT_QUORUM_PROOF --network mainnet -- get_active_schema_version

Confirm this returns 1 (the v1 schema registered during initialize).

3.3 End-to-end smoke test

Using a disposable, low-value test credential (not a real credential holder's data):

  1. Issue a test credential through quorum_proof
  2. Attest it from a test attestor account
  3. Confirm the credential's attestation state reflects the attestation
  4. If sbt_registry is wired to quorum_proof, confirm the corresponding SBT was minted and that a transfer() call on it is rejected with SoulboundNonTransferable (see ADR-002) — this is a cheap, high-signal check that the non-transferability invariant survived deployment
  5. Revoke the test credential and confirm it is reflected as revoked

Full command sequences for each of these are in docs/deployment-guide.md §8.

3.4 Monitoring confirmation

Confirm the dashboards from docs/monitoring-guide.md are receiving events from the new contract IDs, not stale data from a previous deployment. Confirm alerting is wired to the new contract IDs specifically — a monitoring config left pointed at old testnet or previous mainnet contract IDs will silently fail to alert on real incidents.

3.5 Sign-off

Both operators (executor and reader, from the top of this document) record explicit sign-off in the deployment ticket with timestamp, before the deployment window is considered closed.


4. Rollback Procedures

Decide which rollback path applies based on severity, then execute it. Full command sequences for each path are in docs/deployment-guide.md §6 and docs/disaster-recovery.md — this section is the decision tree, not a duplicate of those commands.

4.1 Decide the severity

Situation Path
A non-critical bug found post-deployment, contract state is otherwise healthy §4.2 Contract upgrade rollback
An active exploit or critical vulnerability is being exploited right now §4.3 Emergency pause (immediately), then evaluate upgrade vs. redeploy
Admin key compromise, or initialization was performed with the wrong admin address §4.4 Full redeployment

4.2 Contract upgrade rollback (non-critical regression)

Use when the previous WASM is known-good and on-chain state does not need to change. Follow docs/deployment-guide.md §6.1 and docs/contract-upgrade-strategy.md. Requires the admin multisig to approve the upgrade call — budget time for signer coordination; this is not an instant action.

4.3 Emergency pause (active exploit)

This is the only rollback action that should happen without waiting for full multisig coordination time if signers are reachable quickly — the goal is to stop damage first, investigate second. Follow docs/deployment-guide.md §6.2. After pausing:

  1. Confirm read-only functions still work and write functions are blocked
  2. Investigate root cause before unpausing
  3. Do not unpause until a patched, reviewed, tested contract is ready to deploy — unpausing the vulnerable contract "temporarily" re-exposes the same exploit

4.4 Full redeployment (key compromise or bad initialization)

The most expensive path — on-chain state from the compromised contracts is not automatically migrated. Follow docs/deployment-guide.md §6.3 and docs/disaster-recovery.md in full. Before starting, notify all issuers and credential holders that re-issuance will be required — this is a coordination-heavy process, not a pure technical one, and the coordination should start in parallel with the technical redeployment, not after it.

4.5 Post-rollback verification

Whichever path was taken, re-run §3 (Post-Deployment Verification) in full against the post-rollback state before declaring the incident resolved.